1997 Newsletter McNulty WATER ASSOCIATION
34240 Millard Rd. Warren OR 97053


RETIRING THE MORTGAGES fast.
	Last winter we were forced by  government 
lending agencies to take rapid action to pay back some 
$166,000 in debt owed by McNulty Water. These debts 
are 30 year loans that financed the construction of much of 
the water system. Some are old  - 1964 construction as the 
system was first built. Some are newer - the Stone Road 
well & pump in 1977.
	At the February 1996 meeting, those members 
present voted overwhelmingly to retire the debt rapidly. 
The board implemented an Eight Dollar a Month  
SURCHARGE on each meter.  This extra $24 per billing 
is bringing in more than $17,000 per billing, all of which 
is being used to retire the long term debts. Three of the 
six bonds have been paid off this year, with the 
SURCHARGE money.
	As expected, the $166,000 debt will be fully 
retired after ten such billings. The last billing showing the 
surcharge should be the second billing in 1998. At that 
time, the surcharge will end.
	NO RATE INCREASES.  The board is pleased 
with the willingness of the majority to get this financial 
burden behind us. The board has felt that we should try to 
get along with NO INCREASES IN BASIC RATES during 
the period of  the surcharge.
	The highway project presented us with an 
extreme financial challenge.  With the help of the money 
in hand, and of the surcharge to prevent a double problem, 
and of careful deferring of some other expansion projects, 
we managed to finish the summer with as near to ZERO in 
the bank as one could. We took out NO new bank debt. 

HIGHWAY 30 CONSTRUCTION
	Our new water line along the highway replaces 
some of the oldest line in the system. It runs near  the new  
PUD pole line.
	The south end of the line is at Dave Road, a 
quarter mile north of Bennett Road. There is a new feed 
from the south end of Bayview Ridge, along Dave Road, to 
the highway.
	Rearranged feeds come to the highway along 
Achilles Road, Millard Road, and Division Road.

	The main line continues North to Firway Lane. 
Much of the Firway Lane arrangement has been brought 
up to date, with two new hydrants on Firway.
	In earlier decades, water was bought from St. 
Helens through a connection at McNulty Creek. Our 
furthest North customer was the Veterinarian.  We no 
longer cross the creek. We have abandoned the connection 
to St. Helens water at this point.
	The STATE does NOT pay for the costs of 
relocating utilities when a road is modified. Thus, 
McNulty Water has paid for ALL the costs of 
replacing the 7000 feet of water main along the 
highway, installing new hydrants, and reconnecting 
to all residents. The biggest single expense was a 
highway crossing and boring under the railroad, at 
Millard Rd., to serve those houses east of the 
highway.
Actual costs to us were more than $150,000.


ANNUAL PUBLIC MEETING of the McNulty Water Association
Tuesday, February 18, 1997,  7:00 PM McNulty Office,
 34240 Millard Road   All  are  welcome.


ALL CROSS-CONNECTION PREVENTION DEVICES 
ARE TO BE TESTED IN THE MONTH OF MARCH. 
Each owner of a back-flow prevention device must have the 
device tested before March 31. Your report from a certified 
tester must be on file at the McNulty Water Office by March 
31.  	Otherwise, the law requires the shutoff of your 
water service.
	It is the owners responsibility to see that the white 
copy of your test is turned in to McNulty Water by March 31.

AMONG THE QUALIFIED TESTERS:
Back Flow Management    1-800-824-4385
Water Metrics    1-800-523-1884
Robert (Bo) Laird   397-4677
Steve Wagner    641-4983,  626-8783
Richard Sattler 537-0334 or 351-5321
Above notice is for those 35 or so members who have 
legally required cross connection prevention devices.


REPORT TO CONSUMERS 
Regarding McNulty Water Supply:
WE CONTINUE TO SUPPLY GOOD WATER
	This report is in response to recent EPA 
implementation of the SAFE DRINKING WATER ACT 
amendments of 1996.
	MCNULTY WATER SERVES 750 WATER 
CONNECTIONS, as of December 1996. We are thus a 
“Small System, serving fewer than 10,000 people”. There 
are 186,000 public water systems in the USA.
	WE HAVE ENOUGH WATER.  We have five 
wells. Four of them are currently operable (with pumps and 
power supply). Three of the four can be operated at one 
time. Any two of the three could keep up with the demand 
for water in summer. Thus we feel we have a comfortable 
safety margin. We could pump nearly one million gallons a 
day. We usually pump about one half million gallons a day 
on hot days.
	WE HAVE NEVER HAD A TURBIDITY 
PROBLEM. Our wells are ALL DEEP WELLS, drawing 
water from two to four hundred feet below the surface, well 
below the first levels of rock. Thus, they are not affected by 
river level, by storm runoff, or by other problems 
experienced in, for example, St. Helens.
	EVERY WELL PASSES THE STATE TESTS 
for contaminants. These regular test are run on a state-
mandated schedule. Chemical and biological tests are done 
by an outside laboratory.
	With a pathogen-free water source, we never have 
a well problem that requires the addition of  chlorine. When 
a line has been extended or replaced, chlorine is used in that 
section only until the water at the far end of the line passes 
purity tests. New lines are not connected to customers until 
they pass the tests, or else the customers at each home are 
warned that the tests have not yet been completed.
=============================
	Chemical Measurements of McNulty water have 
shown no reasons for concern:
Chlorine: None
Natural Fluoride: 0.15 mg/L,  which is
   4 percent of the 4.0 mg/L limit.
Added Fluoride: None
Negligible levels of NINETEEN inorganic chemicals. No 
lead, no mercury, no arsenic, no asbestos.
Negligible levels of  EIGHTY THREE organic 
chemicals.
==============================
Local measurement of pH: Typically 7.2

THE BOOSTER PUMP for the NORTHERN 
CUSTOMERS
	Customers north of the Fairgrounds receive 
their water from the 200,000 gallon tank on 
Robinette Road. Water is pumped from the tanks at 
Blaha Road to the tank at Robinette by a BOOSTER 
PUMP, located in a pit at the West entrance to the 
fairgrounds.
	We try to have two sources of water to all 
main water lines. This is done by bringing water 
around the blocks, just as roads go around blocks, 
and as power lines go around groups of houses. 
	We have many such loops. One is the block 
of Millard, Bachelor Flat & Ross Road. Another 
includes Sykes Road, Pittsburg Road, and East and 
West Kappler roads.
	The feed past the fairgrounds is one of our 
links which has no backup. There is no second line 
along Saulser Road. 
	THIS YEAR, we took one more step 
toward dependability by buying as SECOND 
BOOSTER PUMP.  It is now in use at the 
fairgrounds site. The old pump is removed, and is 
being rebuilt. This pump will remain ready to put 
back into service if needed.  How much for a pump 
like that? $3000. It pumps 300 gallons a minute 
against a head of 80 to 100 PSI.
	NEXT YEAR, we want to improve the line 
to, and from, the Robinette Tank. The line is too 
small, causing variations in pressure for those north 
of the Fairgrounds.
	The first step will be draining the Robinette 
tank, adding a twelve inch outlet and valve at the 
bottom, and repainting the inside if necessary.  This 
can’t happen until the weather is warm enough for 
painting.


The NATIONAL DRINKING WATER 
CLEARINGHOUSE has a website:     
www.ndwc.wvu.edu


There are about 800 new homes in St. Helens in the last 
two years.
 There are about  40 new homes in the McNulty area in 
the last two years.
==========================
McNulty Board: Richard Louie, Walt Neaderhiser, Mae Mowrey, 
Steve Rosenlund, Noel Thompson.
Significant Others: Ben Erlandson, Fred Bolton, Melvin Olson
e:\ww\water\news9701.doc Printed 7 July, 1999
<\pre><\html>